Improvement updates


  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Harry Hartman

 

  

Contact Number:

 

  

623.222.6000

 

Sign Fabrication Shop  

 

  

LAST UPDATED:

 

  

10/7/2007

 

  

PROJECT NUMBER:

 

20651  

 

  

CURRENT PHASE:

 

  

PROCUREMENT

 

  

% COMPLETE:

 

  

42%

 

  

PROJECT BUDGET:

 

901,000.00$  

 

  

EST COMPLETION:

 

  

March 2008

 

  

TOTAL EXPENDED:

 

107,800.00$  

 

  

UPDATE SYNOPSIS:

 

  

The Construction Documents (CD) for the building have been completed and permitted by the State Manufactured Housing Board. Fabrication of the facility has commenced. Becausof the uniqueness of the site and the surrounding areas, the team is seeking direction on how to proceed with the design of the site drainage system.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Terry Lowe

 

  

Contact Number:

 

  

623.222.6000

 

City Hall  

 

  

LAST UPDATED:

 

  

10/10/2007

 

  

PROJECT NUMBER:

 

20675  

 

  

CURRENT PHASE:

 

  

DESIGN

 

  

% COMPLETE:

 

  

53%

 

  

PROJECT BUDGET:

 

60,607,800.00$  

 

  

EST COMPLETION:

 

  

December 2008

 

  

TOTAL EXPENDED:

 

4,203,761.00$  

 

  

UPDATE SYNOPSIS:

 

  

The Project Team has received approved building plans from the Community Development Department and are anticipating Engineering approval the first part of October. Excavation for the building pad for the parking garage has begun.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Terry Lowe

 

  

Contact Number:

 

  

623.222.6000

 

Streetscape  

 

  

LAST UPDATED:

 

  

10/7/2007

 

  

PROJECT NUMBER:

 

20676  

 

  

CURRENT PHASE:

 

  

CONSTRUCTION

 

  

% COMPLETE:

 

  

99%

 

  

PROJECT BUDGET:

 

5,313,300.00$  

 

  

EST COMPLETION:

 

  

October 2008

 

  

TOTAL EXPENDED:

 

4,085,880.00$  

 

  

UPDATE SYNOPSIS:

 

  

The Streetscape is all but complete, the last of the planting was installed, the fountain was activated, and Flags were hung. The punch list of the last remaining items was also developed in September.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Terry Lowe

 

  

Contact Number:

 

  

623.222.6000

 

Central Plant  

 

  

LAST UPDATED:

 

  

10/9/2007

 

  

PROJECT NUMBER:

 

20677  

 

  

CURRENT PHASE:

 

  

CONSTRUCTION

 

  

% COMPLETE:

 

  

99%

 

  

PROJECT BUDGET:

 

8,178,900.00$  

 

  

EST COMPLETION:

 

  

October 2007

 

  

TOTAL EXPENDED:

 

5,922,687.00$  

 

  

UPDATE SYNOPSIS:

 

  

The punch list approximately 90% complete. The last of the landscape that is associated with the Central Plant began installation in September.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Harry Hartman

 

  

Contact Number:

 

  

623.222.6000

 

Fire Station #7  

 

  

LAST UPDATED:

 

  

10/7/2007

 

  

PROJECT NUMBER:

 

20702  

 

  

CURRENT PHASE:

 

  

PROCUREMENT

 

  

% COMPLETE:

 

  

50%

 

  

PROJECT BUDGET:

 

5,317,000.00$  

 

  

EST COMPLETION:

 

  

May 2008

 

  

TOTAL EXPENDED:

 

427,383.00$  

 

  

UPDATE SYNOPSIS:

 

  

The Project Team received the first round of comments from the permit review process. The comments were addressed and resubmitted to the City. The Guaranteed Maximum Price (GMP) was approved by Council Sept 13th.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Terry Lowe

 

  

Contact Number:

 

  

623.222.6000

 

Public Works Yard - Deer Valley  

 

  

LAST UPDATED:

 

  

10/7/2007

 

  

PROJECT NUMBER:

 

20717  

 

  

CURRENT PHASE:

 

  

PROCUREMENT

 

  

% COMPLETE:

 

  

0%

 

  

PROJECT BUDGET:

 

10,600,000.00$  

 

  

EST COMPLETION:

 

  

June 2010

 

  

TOTAL EXPENDED:

 

-$  

 

  

UPDATE SYNOPSIS:

 

  

Currently the City’s Water Services Department is developing a site master plan study by which SPA3 (Special Planning Area) will be constructed and expanded over the next several years. As part of the Master Site Plan, an area will be designated for the New Public Works Yard.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Fred Stevens

 

  

Contact Number:

 

  

623.222.6000

 

Bicentennial Park - Enhancement  

 

  

LAST UPDATED:

 

  

10/7/2007

 

  

PROJECT NUMBER:

 

20733  

 

  

CURRENT PHASE:

 

  

DESIGN

 

  

% COMPLETE:

 

  

58%

 

  

PROJECT BUDGET:

 

1,000,000.00$  

 

  

EST COMPLETION:

 

  

June 2008

 

  

TOTAL EXPENDED:

 

149,290.00$  

 

  

UPDATE SYNOPSIS:

 

  

September saw a lot of change come to Bicentennial Park. All of the excess soil from the Lizard Run project, in addition to imported soil, was placed to raise the park play areas. Also, the existing parking lot was removed in preparation for new parking that will extend from the park to the Lizard Run project.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Harry Hartman

 

  

Contact Number:

 

  

623.222.6000

 

Gaines Park Restrooms  

 

  

LAST UPDATED:

 

  

10/1/2007

 

  

PROJECT NUMBER:

 

20802  

 

  

CURRENT PHASE:

 

  

DESIGN

 

  

% COMPLETE:

 

  

40%

 

  

PROJECT BUDGET:

 

225,000.00$  

 

  

EST COMPLETION:

 

  

January 2008

 

  

TOTAL EXPENDED:

 

3,973.00$  

 

  

UPDATE SYNOPSIS:

 

  

Design and plan review complete. Planned advertising for construction no later than 10/05/07. To council no later than 11/8/07.

 

 

 

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Harry Hartman

 

Contact Number:

 

623.222.6000

Santa Fe Fence 

 

LAST UPDATED:

 

10/1/2007

 

PROJECT NUMBER:

20803 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

0%

 

PROJECT BUDGET:

440,000.00$ 

 

EST COMPLETION:

 

January 1900

 

TOTAL EXPENDED:

-$ 

 

UPDATE SYNOPSIS:

 

Fence cannot be constructed at this time. Waiting for right-of-way approval by Burlington Northern Santa Fe (BNSF) railroad. City has contacted BNSF and requested approval for placement of fence in their right-of-way. However, this could take 6 months to 2 years for approval.

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Dave Kohlbeck

 

Contact Number:

 

623.222.6025

Alley Improvements 

 

LAST UPDATED:

 

10/1/2007

 

PROJECT NUMBER:

20804 

 

CURRENT PHASE:

 

PROCUREMENT

 

% COMPLETE:

 

0%

 

PROJECT BUDGET:

100,000.00$ 

 

EST COMPLETION:

 

December 2007

 

TOTAL EXPENDED:

-$ 

 

UPDATE SYNOPSIS:

 

Limited response from residents on right-of-way dedication to city. Staff planning on giving council update at the October 23rd meeting with options on how to proceed.

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Fred Stevens

 

Contact Number:

 

623.222.6000

Aquatics Facility #3 

 

LAST UPDATED:

 

10/7/2007

 

PROJECT NUMBER:

20806 

 

CURRENT PHASE:

 

PROCUREMENT

 

% COMPLETE:

 

1%

 

PROJECT BUDGET:

650,000.00$ 

 

EST COMPLETION:

 

May 2010

 

TOTAL EXPENDED:

-$ 

 

UPDATE SYNOPSIS:

 

Project Management drafted the Design Services Request for Qualifications (RFQ) for the Aquatic Facility #3. The RFQ has been forwarded to the project’s stakeholders for review and comment.

 

Department:

 

WATER SERVICES

 

Project Manager:

 

Kinga Stanek

 

Contact Number:

 

623.222.7037

SPA 1 Installation of Recharge Wells @ South Plant 

 

LAST UPDATED:

 

10/5/2007

 

PROJECT NUMBER:

20234 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

40%

 

PROJECT BUDGET:

4,030,000.00$ 

 

EST COMPLETION:

 

June 2008

 

TOTAL EXPENDED:

310,494.00$ 

 

UPDATE SYNOPSIS:

 

Project Team received 100% drawings and specifications, these are in process of review and final approval for advertisement. Project Team had a pre-application meeting with ADWR (Arizona Department of Water Resources) to initiate review of the application.

 

Department:

 

WATER SERVICES

 

Project Manager:

 

Nancy Eberlein

 

Contact Number:

 

623.222.7027

SPA 1 Surprise Center Well Construction 

 

LAST UPDATED:

 

10/8/2007

 

PROJECT NUMBER:

20244 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

52%

 

PROJECT BUDGET:

1,051,600.00$ 

 

EST COMPLETION:

 

December 2007

 

TOTAL EXPENDED:

84,334.00$ 

 

UPDATE SYNOPSIS:

 

Physical construction has begun! Survey completed, Arizona Public Service (APS) conduit run from the ballpark office north to Paradise Lane, concrete has been formed, poured and finished. Underground well equipment will soon follow.

 

Department:

 

WATER SERVICES

 

Project Manager:

 

Christine Nuñez

 

Contact Number:

 

623.222.7035

SPA 1 Groundwater Savings Facility Permits 

 

LAST UPDATED:

 

10/1/2007

 

PROJECT NUMBER:

20415 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

13%

 

PROJECT BUDGET:

430,000.00$ 

 

EST COMPLETION:

 

August 2008

 

TOTAL EXPENDED:

16,450.00$ 

 

UPDATE SYNOPSIS:

 

Project delayed until we can get a meeting with the City of Phoenix to negotiate use on their land

 

Department:

 

WATER SERVICES

 

Project Manager:

 

Todd Gillam

 

Contact Number:

 

623.222.7026

SPA 1 16-in Reclaimed Line Statler to Bell Road Lake 

 

LAST UPDATED:

 

10/2/2007

 

PROJECT NUMBER:

20418 

 

CURRENT PHASE:

 

PROCUREMENT

 

% COMPLETE:

 

8%

 

PROJECT BUDGET:

1,650,000.00$ 

 

EST COMPLETION:

 

December 2009

 

TOTAL EXPENDED:

114,792.00$ 

 

UPDATE SYNOPSIS:

 

The contract has been signed by Dibble Engineering and our Budget Department. The contract is now in the Legal Department awaiting the attorneys’ signature.

 

Department:

 

WATER SERVICES

 

Project Manager:

 

Christine Nuñez

 

Contact Number:

 

623.222.7035

SPA 1 Litchfield Road WRF Decommission 

 

LAST UPDATED:

 

10/1/2007

 

PROJECT NUMBER:

20459 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

98%

 

PROJECT BUDGET:

100,000.00$ 

 

EST COMPLETION:

 

September 2007

 

TOTAL EXPENDED:

31,153.00$ 

 

UPDATE SYNOPSIS:

 

The Litchfield WRF (Water Reclamation Facility) is currently demolished. The City has submitted the clean closure application and is awaiting response/approval of the closure. No change in the past month as the clean closure process may take several months to obtain