Improvement updates
|
Department:
|
PUBLIC WORKS
|
Project Manager:
|
Harry Hartman
|
Contact Number:
|
623.222.6000
|
|||||
| Sign Fabrication Shop
|
LAST UPDATED:
|
10/7/2007
|
||||||||
|
PROJECT NUMBER:
|
20651
|
CURRENT PHASE:
|
PROCUREMENT
|
|||||||
|
% COMPLETE:
|
42%
|
PROJECT BUDGET:
|
901,000.00$
|
|||||||
|
EST COMPLETION:
|
March 2008
|
TOTAL EXPENDED:
|
107,800.00$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
The Construction Documents (CD) for the building have been completed and permitted by the State Manufactured Housing Board. Fabrication of the facility has commenced. Becausof the uniqueness of the site and the surrounding areas, the team is seeking direction on how to proceed with the design of the site drainage system.
|
||||||||||
|
Department:
|
PUBLIC WORKS
|
Project Manager:
|
Terry Lowe
|
Contact Number:
|
623.222.6000
|
|||||
| City Hall
|
LAST UPDATED:
|
10/10/2007
|
||||||||
|
PROJECT NUMBER:
|
20675
|
CURRENT PHASE:
|
DESIGN
|
|||||||
|
% COMPLETE:
|
53%
|
PROJECT BUDGET:
|
60,607,800.00$
|
|||||||
|
EST COMPLETION:
|
December 2008
|
TOTAL EXPENDED:
|
4,203,761.00$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
The Project Team has received approved building plans from the Community Development Department and are anticipating Engineering approval the first part of October. Excavation for the building pad for the parking garage has begun.
|
||||||||||
|
Department:
|
PUBLIC WORKS
|
Project Manager:
|
Terry Lowe
|
Contact Number:
|
623.222.6000
|
|||||
| Streetscape
|
LAST UPDATED:
|
10/7/2007
|
||||||||
|
PROJECT NUMBER:
|
20676
|
CURRENT PHASE:
|
CONSTRUCTION
|
|||||||
|
% COMPLETE:
|
99%
|
PROJECT BUDGET:
|
5,313,300.00$
|
|||||||
|
EST COMPLETION:
|
October 2008
|
TOTAL EXPENDED:
|
4,085,880.00$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
The Streetscape is all but complete, the last of the planting was installed, the fountain was activated, and Flags were hung. The punch list of the last remaining items was also developed in September.
|
||||||||||
|
Department:
|
PUBLIC WORKS
|
Project Manager:
|
Terry Lowe
|
Contact Number:
|
623.222.6000
|
|||||
| Central Plant
|
LAST UPDATED:
|
10/9/2007
|
||||||||
|
PROJECT NUMBER:
|
20677
|
CURRENT PHASE:
|
CONSTRUCTION
|
|||||||
|
% COMPLETE:
|
99%
|
PROJECT BUDGET:
|
8,178,900.00$
|
|||||||
|
EST COMPLETION:
|
October 2007
|
TOTAL EXPENDED:
|
5,922,687.00$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
The punch list approximately 90% complete. The last of the landscape that is associated with the Central Plant began installation in September.
|
||||||||||
|
Department:
|
PUBLIC WORKS
|
Project Manager:
|
Harry Hartman
|
Contact Number:
|
623.222.6000
|
|||||
| Fire Station #7
|
LAST UPDATED:
|
10/7/2007
|
||||||||
|
PROJECT NUMBER:
|
20702
|
CURRENT PHASE:
|
PROCUREMENT
|
|||||||
|
% COMPLETE:
|
50%
|
PROJECT BUDGET:
|
5,317,000.00$
|
|||||||
|
EST COMPLETION:
|
May 2008
|
TOTAL EXPENDED:
|
427,383.00$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
The Project Team received the first round of comments from the permit review process. The comments were addressed and resubmitted to the City. The Guaranteed Maximum Price (GMP) was approved by Council Sept 13th.
|
||||||||||
|
Department:
|
PUBLIC WORKS
|
Project Manager:
|
Terry Lowe
|
Contact Number:
|
623.222.6000
|
|||||
| Public Works Yard - Deer Valley
|
LAST UPDATED:
|
10/7/2007
|
||||||||
|
PROJECT NUMBER:
|
20717
|
CURRENT PHASE:
|
PROCUREMENT
|
|||||||
|
% COMPLETE:
|
0%
|
PROJECT BUDGET:
|
10,600,000.00$
|
|||||||
|
EST COMPLETION:
|
June 2010
|
TOTAL EXPENDED:
|
-$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
Currently the City’s Water Services Department is developing a site master plan study by which SPA3 (Special Planning Area) will be constructed and expanded over the next several years. As part of the Master Site Plan, an area will be designated for the New Public Works Yard.
|
||||||||||
|
Department:
|
PUBLIC WORKS
|
Project Manager:
|
Fred Stevens
|
Contact Number:
|
623.222.6000
|
|||||
| Bicentennial Park - Enhancement
|
LAST UPDATED:
|
10/7/2007
|
||||||||
|
PROJECT NUMBER:
|
20733
|
CURRENT PHASE:
|
DESIGN
|
|||||||
|
% COMPLETE:
|
58%
|
PROJECT BUDGET:
|
1,000,000.00$
|
|||||||
|
EST COMPLETION:
|
June 2008
|
TOTAL EXPENDED:
|
149,290.00$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
September saw a lot of change come to Bicentennial Park. All of the excess soil from the Lizard Run project, in addition to imported soil, was placed to raise the park play areas. Also, the existing parking lot was removed in preparation for new parking that will extend from the park to the Lizard Run project.
|
||||||||||
|
Department:
|
PUBLIC WORKS
|
Project Manager:
|
Harry Hartman
|
Contact Number:
|
623.222.6000
|
|||||
| Gaines Park Restrooms
|
LAST UPDATED:
|
10/1/2007
|
||||||||
|
PROJECT NUMBER:
|
20802
|
CURRENT PHASE:
|
DESIGN
|
|||||||
|
% COMPLETE:
|
40%
|
PROJECT BUDGET:
|
225,000.00$
|
|||||||
|
EST COMPLETION:
|
January 2008
|
TOTAL EXPENDED:
|
3,973.00$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
Design and plan review complete. Planned advertising for construction no later than 10/05/07. To council no later than 11/8/07.
|
||||||||||
|
Department: |
PUBLIC WORKS |
Project Manager: |
Harry Hartman |
Contact Number: |
623.222.6000 |
|||||
| Santa Fe Fence |
LAST UPDATED: |
10/1/2007 |
||||||||
|
PROJECT NUMBER: |
20803 |
CURRENT PHASE: |
DESIGN |
|||||||
|
% COMPLETE: |
0% |
PROJECT BUDGET: |
440,000.00$ | |||||||
|
EST COMPLETION: |
January 1900 |
TOTAL EXPENDED: |
-$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
Fence cannot be constructed at this time. Waiting for right-of-way approval by Burlington Northern Santa Fe (BNSF) railroad. City has contacted BNSF and requested approval for placement of fence in their right-of-way. However, this could take 6 months to 2 years for approval. |
||||||||||
|
Department: |
PUBLIC WORKS |
Project Manager: |
Dave Kohlbeck |
Contact Number: |
623.222.6025 |
|||||
| Alley Improvements |
LAST UPDATED: |
10/1/2007 |
||||||||
|
PROJECT NUMBER: |
20804 |
CURRENT PHASE: |
PROCUREMENT |
|||||||
|
% COMPLETE: |
0% |
PROJECT BUDGET: |
100,000.00$ | |||||||
|
EST COMPLETION: |
December 2007 |
TOTAL EXPENDED: |
-$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
Limited response from residents on right-of-way dedication to city. Staff planning on giving council update at the October 23rd meeting with options on how to proceed. |
||||||||||
|
Department: |
PUBLIC WORKS |
Project Manager: |
Fred Stevens |
Contact Number: |
623.222.6000 |
|||||
| Aquatics Facility #3 |
LAST UPDATED: |
10/7/2007 |
||||||||
|
PROJECT NUMBER: |
20806 |
CURRENT PHASE: |
PROCUREMENT |
|||||||
|
% COMPLETE: |
1% |
PROJECT BUDGET: |
650,000.00$ | |||||||
|
EST COMPLETION: |
May 2010 |
TOTAL EXPENDED: |
-$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
Project Management drafted the Design Services Request for Qualifications (RFQ) for the Aquatic Facility #3. The RFQ has been forwarded to the project’s stakeholders for review and comment. |
||||||||||
|
Department: |
WATER SERVICES |
Project Manager: |
Kinga Stanek |
Contact Number: |
623.222.7037 |
|||||
| SPA 1 Installation of Recharge Wells @ South Plant |
LAST UPDATED: |
10/5/2007 |
||||||||
|
PROJECT NUMBER: |
20234 |
CURRENT PHASE: |
DESIGN |
|||||||
|
% COMPLETE: |
40% |
PROJECT BUDGET: |
4,030,000.00$ | |||||||
|
EST COMPLETION: |
June 2008 |
TOTAL EXPENDED: |
310,494.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
Project Team received 100% drawings and specifications, these are in process of review and final approval for advertisement. Project Team had a pre-application meeting with ADWR (Arizona Department of Water Resources) to initiate review of the application. |
||||||||||
|
Department: |
WATER SERVICES |
Project Manager: |
Nancy Eberlein |
Contact Number: |
623.222.7027 |
|||||
| SPA 1 Surprise Center Well Construction |
LAST UPDATED: |
10/8/2007 |
||||||||
|
PROJECT NUMBER: |
20244 |
CURRENT PHASE: |
DESIGN |
|||||||
|
% COMPLETE: |
52% |
PROJECT BUDGET: |
1,051,600.00$ | |||||||
|
EST COMPLETION: |
December 2007 |
TOTAL EXPENDED: |
84,334.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
Physical construction has begun! Survey completed, Arizona Public Service (APS) conduit run from the ballpark office north to Paradise Lane, concrete has been formed, poured and finished. Underground well equipment will soon follow. |
||||||||||
|
Department: |
WATER SERVICES |
Project Manager: |
Christine Nuñez |
Contact Number: |
623.222.7035 |
|||||
| SPA 1 Groundwater Savings Facility Permits |
LAST UPDATED: |
10/1/2007 |
||||||||
|
PROJECT NUMBER: |
20415 |
CURRENT PHASE: |
DESIGN |
|||||||
|
% COMPLETE: |
13% |
PROJECT BUDGET: |
430,000.00$ | |||||||
|
EST COMPLETION: |
August 2008 |
TOTAL EXPENDED: |
16,450.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
Project delayed until we can get a meeting with the City of Phoenix to negotiate use on their land |
||||||||||
|
Department: |
WATER SERVICES |
Project Manager: |
Todd Gillam |
Contact Number: |
623.222.7026 |
|||||
| SPA 1 16-in Reclaimed Line Statler to Bell Road Lake |
LAST UPDATED: |
10/2/2007 |
||||||||
|
PROJECT NUMBER: |
20418 |
CURRENT PHASE: |
PROCUREMENT |
|||||||
|
% COMPLETE: |
8% |
PROJECT BUDGET: |
1,650,000.00$ | |||||||
|
EST COMPLETION: |
December 2009 |
TOTAL EXPENDED: |
114,792.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
The contract has been signed by Dibble Engineering and our Budget Department. The contract is now in the Legal Department awaiting the attorneys’ signature. |
||||||||||
|
Department: |
WATER SERVICES |
Project Manager: |
Christine Nuñez |
Contact Number: |
623.222.7035 |
|||||
| SPA 1 Litchfield Road WRF Decommission |
LAST UPDATED: |
10/1/2007 |
||||||||
|
PROJECT NUMBER: |
20459 |
CURRENT PHASE: |
DESIGN |
|||||||
|
% COMPLETE: |
98% |
PROJECT BUDGET: |
100,000.00$ | |||||||
|
EST COMPLETION: |
September 2007 |
TOTAL EXPENDED: |
31,153.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
The Litchfield WRF (Water Reclamation Facility) is currently demolished. The City has submitted the clean closure application and is awaiting response/approval of the closure. No change in the past month as the clean closure process may take several months to obtain |
||||||||||